WD Walledge Davis Consulting Limited

Installer & contractor support

G99 application support for solar PV, EV charging & battery projects

Practical DNO application and grid connection support for installers, developers and electrical contractors across Great Britain.

Best suited to commercial and light industrial schemes where export capacity, reinforcement, G100 export limitation or DNO technical queries could affect cost or programme.

Currently accepting installer and contractor enquiries for Q2/Q3 2026

Typical support

• G98/G99 application support

• Commercial solar DNO applications

• Single line diagram review

• Import/export capacity advice

• G100 export limitation advice

• EV charger DNO application support

• Heat pump and electrification load review

• DNO offer and query support

Pricing

What it costs

Commercial G99 application support from £450 + VAT. Complex or multi-technology sites — including co-located solar and BESS, or sites with export limitation requirements — are quoted on scope.

Get in touch with a short project overview and you’ll get a clear fee within one business day.

Support for projects that have outgrown basic installer applications

Some projects are not complicated enough to justify a large consultancy team, but are too important to treat as a form-filling exercise.

That is usually where DNO capacity, export limits, reinforcement costs, equipment assumptions or technical queries start affecting customer price, programme or feasibility.

Typical projects

  • • Commercial rooftop solar PV
  • • Farm, estate and industrial solar projects
  • • EV charging hubs and depot electrification
  • • Heat pump and wider electrification upgrades
  • • Small BESS and co-located PV + battery systems
  • • Projects with constrained export or reinforcement exposure

Typical support ranges from commercial-scale schemes through to multi-MW distribution-connected projects.

Commercial schemes

Commercial G99 applications are different

Most G99 support services are built around high-volume domestic installs. Commercial and light industrial schemes — typically 50kW to 1MW — involve a different level of complexity: export limitation strategy, multi-technology arrangements, reinforcement risk, and DNO technical queries that require more than form-filling to resolve.

This support is aimed at installers and contractors who need someone who understands the network, not just the paperwork. If the DNO comes back with a position you’re not comfortable with, or the connection arrangement is affecting your commercial offer to the end customer, that’s where this service adds most value.

G98, G99 and G100 — practical thresholds

G98

Generally applies to fully type-tested microgeneration up to and including 16A per phase.

Approximate limits: 3.68kW single-phase or 11.04kW three-phase.

G99

Applies where generation or storage exceeds 16A per phase, or where the installation falls outside G98 requirements.

Usually requires DNO assessment and approval before commissioning.

G100

Relevant where installed capacity is greater than the agreed export limit and export limitation is used to stay within the DNO-approved export capacity.

Common on commercial solar PV, BESS and constrained sites.

Typical G99 process

The exact route depends on project size, voltage level, DNO and site arrangement, but most installer-led commercial projects follow a version of this process.

  1. Confirm site demand, generation/storage capacity and import/export assumptions.
  2. Check whether G98, G99, G100 or EV/heat pump DNO processes apply.
  3. Prepare technical inputs, including SLDs, equipment details and capacity assumptions.
  4. Submit to the relevant DNO with complete supporting information.
  5. DNO carries out network assessment and raises technical queries where needed.
  6. Review approval, connection offer, reinforcement, export limits or conditions.
  7. Support close-out, commissioning inputs or follow-up queries where required.

Typical timeframes

G98 single premises

Often a connect-and-notify route where the DNO is notified after installation, provided all G98 conditions are met.

G99 LV projects

Often planned around a DNO response period of around 45 working days once a complete application has been submitted.

Larger / HV projects

Can be closer to 65 working days or longer, particularly where reinforcement, interactivity, constraints or commercial terms are involved.

Timescales vary by DNO, completeness of information, voltage level, project complexity and network conditions.

Why use Walledge Davis Consulting?

This is not a high-volume admin service. The support is aimed at installers and smaller developers who need senior grid input when a project becomes technically or commercially awkward.

The value is in spotting issues early, giving installers clearer DNO-facing information, and helping avoid avoidable delays, poor assumptions or weak customer commitments.

When to speak to us

  • • Before committing to fixed customer pricing
  • • Before promising installation or energisation dates
  • • Where export, reinforcement or G100 is uncertain
  • • Where the DNO has raised technical questions
  • • Before accepting a connection offer you have not properly reviewed

Frequently asked questions

What is a G99 application?+

A G99 application is the formal DNO process used where generation or storage equipment connects in parallel with the distribution network and falls outside G98 limits. In practice, this usually means systems above 16A per phase, or projects that need a more detailed DNO assessment before installation or commissioning.

What is the difference between G98 and G99?+

G98 generally applies to fully type-tested microgeneration up to and including 16A per phase — approximately 3.68kW on single-phase or 11.04kW on three-phase at nominal voltage. G99 applies above that threshold, or where the installation does not meet the relevant G98 conditions.

What are the usual kW limits for G98?+

At nominal voltage, 16A per phase corresponds to approximately 3.68kW on a single-phase supply and 11.04kW on a three-phase supply. Anything above those limits should normally be considered under G99, although the correct route still depends on the full site arrangement and equipment details.

How long does a G99 application take?+

For many lower-voltage projects, DNO assessment is often planned around a 45 working day response period once the application is complete. Higher-voltage or more complex connections can be longer, commonly around 65 working days or more depending on scope, reinforcement, interactive queue position and DNO requirements.

Can solar PV be installed before G99 approval?+

If the project requires G99 approval, it should not normally be commissioned in parallel with the network until the DNO has approved the connection arrangement. Starting too early can create compliance, programme and commercial issues if the DNO later requires export limitation, reinforcement or a different connection arrangement.

What information does the DNO usually need?+

Typical inputs include site address, MPAN, proposed generation/storage capacity, inverter details, single line diagram, import/export assumptions, protection information, equipment certificates and any export limitation arrangement. Missing or inconsistent information is a common cause of delay.

What is G100/export limitation?+

G100 export limitation is used where installed generation or storage capacity is higher than the agreed export limit. It is common on commercial solar PV and battery projects where the site wants a larger installed system but the DNO will only allow a lower maximum export level.

Do EV chargers require a G99 application?+

EV chargers are demand/load, so they do not normally require G99 by themselves. They may require DNO notification or approval under EV/heat pump connection processes. If EV charging is combined with solar PV, battery storage or export-capable generation, G99 and/or G100 may become relevant.

What causes G99 applications to be delayed or rejected?+

The most common causes are incomplete or inconsistent technical information — missing inverter certificates, incorrect MPAN, mismatched single line diagrams, or export assumptions that don’t align with the proposed equipment.

On more complex sites, failure to identify export limitation requirements early, or submitting without understanding the DNO’s local network constraints, can result in significant delays or unexpected reinforcement costs. Getting the application right first time is almost always faster and cheaper than correcting a rejected submission.

When should an installer speak to a grid consultant?+

Speak before pricing the job, agreeing programme dates, promising export capacity, ordering major equipment or accepting a DNO position you are not comfortable with. Grid issues are usually easier to deal with before the commercial offer to the customer is locked down.

Need support with a G99 or DNO application?

Send a short overview of the project, site location, proposed capacity and the decision you are trying to make.

Response typically within 1 business day.